Our $18.5 million capital project — scheduled for completion in the fall of 2019 — will transform Quail Creek Country Club for the enjoyment of both current and future Members. The project’s innovative, integrated design will enable our Members to play better and longer at their favorite sports and activities, while serving as the hub of their social interactions and friendships.

Our amenities and activities are designed to cater to the ‘whole person’ – physical, mental and social. The centerpiece of the capital project is an integrated sports and fitness center that will be unique in southwest Florida. It will enable us to expand our current offerings and put the Club on the leading edge of tailored services for conditioning and skills enhancement.

This major initiative, along with renovations to our Clubhouse, will provide an overall experience that is everything a country club should be. 

Project Scope

  • $18.5 million capital project to be completed in fall 2019
  • Integrated sports and fitness center that will be unique in Southwest Florida
  • Extended Driving Range and enhanced practice facilities
  • 11 Har-Tru Tennis Courts, including one Exhibition Court
  • 4 Pickleball Courts, 3 Bocce Courts and 1 Croquet Court
  • Expansion of the Greenside Grille kitchen and commissary (food delivery, storage, and prep)
  • New wine room/private dining room
  • New stand-alone casual food/beverage cafe and Cart Barn
  • Updated Clubhouse interior and exterior
  • Updated areas of the Women’s Locker Room
  • Revamped Clubhouse entrance, entrance roads and parking lots

Project Timeline

Summer – Fall 2018  

Completed

Financing arrangements.

Project Schedule for design, permitting and construction, and temporary facilities.

Schematic Design Package, Design Development Documents & Budget, Construction Documents. Subcontractor bids.

Moves to temporary facilities – Golf Pro Shop, Tennis Pro Shop, Bocce courts and Fitness, Wellness & Spa operations.

Filled in the Creek behind the former tennis/fitness buildings to extend the Driving Range and add cart parking. Made other practice facility improvements.

Fall 2018 – Summer 2019

In Progress

Demolish the former tennis and fitness buildings.

Pending

Build the new Sports Center & Spa, which includes a Sports Pro Shop; all Fitness, Wellness & Spa operations; Cart Barn; Staff offices; day lockers/restrooms; hospitality counter; and new entryway. Refresh the pool deck area.

 

Spring 2019 – Fall 2019

Expand the Greenside Grille kitchen and commissary (food delivery, storage and prep). Build a Wine Room.

Update the Women’s Locker Room and bring bathrooms up to code.

 

Fall 2019 – Winter 2019

Demolish the existing Cart Barn and former Golf Pro Shop.

Construct the Creekside Café, a new stand-alone refreshment concession and patio.

 

Early 2020

Build three bocce courts and one croquet court next to the Creekside Cafe.

Re-construct the existing tennis courts, fencing, lighting and changeover areas. Create an exhibition tennis court and four pickleball courts.

Refresh the Clubhouse interior and exterior.

Make parking lot and entry improvements.

12/28/18

 

 